Case Study - Pret a Manger, Paris

Project data

  • Customer
  • Pret a Manger
  • Value
  • Confidential
  • Area
  • 240 sq m
  • Programme duration
  • 15 weeks
  • Completion date
  • 2012

Overview

ISG transformed an empty retail unit in La Défense into France’s first Pret A Manger. Due to the customer’s lease agreement being approved earlier than scheduled, the project started six weeks ahead of the plan.

Early supply chain engagement enabled ISG to reduce long lead times and start the project in line with the new schedule. The ISG team has since delivered a further two stores in Paris and three in the UK.

Pret