Case Study - Paul Smith, Paris

Project data

  • Customer
  • Paul Smith
  • Value
  • Confidential
  • Area
  • 260 sq m
  • Programme duration
  • 7 weeks
  • Completion date
  • November 2012

Introduction

Tenants in occupation, noisy working restrictions and ensuring compliance with building regulations were all challenges ISG encountered while delivering Paul Smith’s brand new womenswear boutique in time for the Christmas period.

Paul Smith Gallery 1

The Project

With just seven weeks to turnaround the conversion of the listed Parisian building, our team devised a schedule of works, that not only ensured the store launched in time, but included the bespoke installation of terrazzo flooring - specially requested by Paul Smith himself.